What to Expect
What to Expect
The following process provides important information on how your custom pool will be designed and built so you will know what to expect.
Week one
- pool layout at excavation one day, 1st draw
- steel installation one day
- plumbing one to two days
- steel, bond and location inspection
Week two
- gunite upon green tag, 2nd draw
- electrical rough in one day
- gas line and p-trap one day
- gas inspection
Week three and four
- tile and coping one week
- deck layout one day
- deck steel inspection
Week five
- deck pour upon green tag one day, 3rd draw
- equipment set one day
- electrical hook up
- gas hook up
Week six
- grade, clean-up and sprinklers one to three days
- fence install one day
- per plaster inspection
- plaster upon green tag
Week seven
- plaster one day
- acid wash plaster one day
- fill pool two days
- start-up pool and let run for three to five days
Week eight
- install jets, salt and all other necessary items
- final inspection
- pool school