The following process provides important information on how your custom pool will be designed and built so you will know what to expect.


Week one


  • pool layout at excavation one day, 1st draw
  • steel installation one day
  • plumbing one to two days
  • steel, bond and location inspection

Week two


  • gunite upon green tag, 2nd draw
  • electrical rough in one day
  • gas line and p-trap one day
  • gas inspection

Week three and four


  • tile and coping one week
  • deck layout one day
  • deck steel inspection

Week five


  • deck pour upon green tag one day, 3rd draw
  • equipment set one day
  • electrical hook up
  • gas hook up

Week six


  • grade, clean-up and sprinklers one to three days
  • fence install one day
  • per plaster inspection
  • plaster upon green tag

Week seven


  • plaster one day
  • acid wash plaster one day
  • fill pool two days
  • start-up pool and let run for three to five days

Week eight


  • install jets, salt and all other necessary items
  • final inspection
  • pool school




 